Since the soil key of the project has been completed before the design, the lowest point is less than 2300mm (the highest equipment is nearly 2100mm), and there is no sunken slab reserved for drainage pipes. The equipment layout and design should be combined with the site conditions to solve the drainage problem;
Due to floor height restrictions, steam parallel pipelines can only go under the suspended ceiling. After multi-faceted communication in the early design and strict on-site supervision of the construction progress, the construction quality still ensures standardized installation, straight pipelines, metal fixed brackets, and clear markings.